Brine pipeline infrastructure
Work began in August 2023 on the DN813 brine pipeline infrastructure under Task I “KZ Broniewice to KS PMR-P” and Task II “KS Mogilno to KZ Broniewice”.
Scope of work
Our scope comprised the complete execution of 14 crossings using pneumatic pipe ramming, with a combined length of 378 m and DN813 pipes.
This archival project was completed under the TECHPOL name. The company now operates as GEOTECHNEX.